DemoSat-R Schedule

08-18-2008

RockSat Payload User’s Guide Released

09-22-2008

Submit Intent to Fly Form

09-29-2008

Initial Down Selections Made

10-27-2008

Earnest Payment of $1,000 Due

10-28-2008

Conceptual Design Review (CoDR) Due

10-28-2008

Online Progress Report 2 Due

11-14-2008

Preliminary Design Review ( PDR) Due

11-28-2008

Online Progress Report 3 Due

12-12-2008

Critical Design Review (CDR) Due

12-19-2008

Final Down Select—Flights Awarded

01-23-2009

First Installment Due

01-30-2009

RockSat Payload Canisters Sent to Customers

01-30-2009

Online Progress Report 4 Due

02-20-2009

Individual Subsystem Testing Reports Due

02-27-2009

Online Progress Report 5 Due

03-27-2009

Payload Subsystem Integration and Testing Report Due

04-10-2009

Final Installment Due

04-17-2009

First Full Mission Simulation Test Report Due

04-30-2009

Online Progress Report 6 Due

05-22-2009

Second Full Mission Simulation Test Report Due

05-29-2009

Online Progress Report 7 Due

06-10-2009

Launch Readiness Review (LRR) Teleconference

06-(22-24)-2009

MOI and Vibration Testing at WFF

06-24-2009

RockSat Payload Canister Integration with WFF

06-26-2009

Launch Day