Schedule: |
08-18-2008 |
RockSat Payload User’s Guide Released |
09-22-2008 |
Submit Intent to Fly Form |
09-29-2008 |
Initial Down Selections Made |
10-27-2008 |
Earnest Payment of $1,000 Due |
10-28-2008 |
Conceptual Design Review (CoDR) Due |
10-28-2008 |
Online Progress Report 2 Due |
11-14-2008 |
Preliminary Design Review (PDR) Due |
11-28-2008 |
Online Progress Report 3 Due |
12-12-2008 |
Critical Design Review (CDR) Due |
12-19-2008 |
Final Down Select—Flights Awarded |
01-23-2009 |
First Installment Due |
01-30-2009 |
RockSat Payload Canisters Sent to Customers |
01-30-2009 |
Online Progress Report 4 Due |
02-20-2009 |
Individual Subsystem Testing Reports Due |
02-27-2009 |
Online Progress Report 5 Due |
03-27-2009 |
Payload Subsystem Integration and Testing Report Due |
04-10-2009 |
Final Installment Due |
04-17-2009 |
First Full Mission Simulation Test Report Due |
04-30-2009 |
Online Progress Report 6 Due |
05-22-2009 |
Second Full Mission Simulation Test Report Due |
05-29-2009 |
Online Progress Report 7 Due |
06-10-2009 |
Launch Readiness Review (LRR) Teleconference |
06-(22-24)-2009 |
MOI and Vibration Testing at WFF |
06-24-2009 |
RockSat Payload Canister Integration with WFF |
06-26-2009 |
Launch Day |