RockSat-C 2013 Schedule

 

This schedule provides the dates for all deliverables and important deadlines for the 2013 RockSat-C program. This schedule is subject to change, and this online version supercedes the schedule in the User's Guide. The last update was made: April 19, 2013. The schedule is tentative. Questions can be directed to Emily Logan at: This email address is being protected from spambots. You need JavaScript enabled to view it.

 


 Spring 2013 Schedule

 

1/18/2013 Final Down Select—Flights Awarded
1/25/2013 Online Progress Report 1 Due 
2/15/2013 Individual Subsystem Testing Reports Due 
2/15/2013 Individual Subsystem Testing Reports Teleconference 
2/18/2013 First payment due
3/12/2013 Online Progress Report 2 Due
3/29/2013 Payload Subsystem Integration and Testing Report Due
4/1/2013 Payload Subsystem Integration and Testing Report Teleconference
4/8/2012 Final payment due
4/15/2013 RockSat Payload Canisters sent to customers *pending receipt of final payment*
5/10/2013*** First Full Mission Simulation Test Report Presentation Due EXTENDED TO THIS DATE
5/10/2013*** First Full Mission Simulation Test Report Presentation Telecon
5/8/2013 Weekly Teleconference 4
5/15/2013 Weekly Teleconference 5
5/29/2013 Weekly Teleconference 6
5/29/2013 Weekly Teleconference 7 (FMSTR 2)
6/3/2013 Launch Readiness Review Presentations 
6/12/2013 Travel to Wallops Flight Facility
6/13/2013 Visual Inspections at Refuge Inn
06/(14-18)/2013 Integration/Vibration at Wallops
6/19/2013 Presentations to next year’s RockSat
6/20/2013 Launch Day!!

 

Fall 2012 Schedule

9/4/2012

RockSat Payload User’s Guide Released

9/17/2012

Deadline to submit Intent to Fly Form

9/24/2012

Initial Down Selections Made

10/5/2012

Conceptual Design Review (CoDR) Due

10/5/2012

Conceptual Design Review (CoDR) Teleconference

10/17/2012

Earnest Payment of $1,000 Due

10/17/2012

Online Progress Report 1 Due

10/26/2012

Preliminary Design Review (PDR) Due

10/26/2012

Preliminary Design Review (PDR) Teleconference

11/9/2012

Online Progress Report 2 Due

11/(16 or 30)/2012

Critical Design Review (CDR) Due – Discuss with teams based on finals schedules

11/28/2012

Critical Design Review (CDR) Teleconference

 

 


COSGC Logo

The RockSat Program is brought to you by

the following programs:

WFF Logo

Go to top