Schedule

This schedule provides the dates for all deliverables and important deadlines for the 2013 RockSat-X program. This schedule is subject to change, and the last update was made: 12/14/12. Launch date is still being determined. Questions can be directed to Chris Koehler at: This email address is being protected from spambots. You need JavaScript enabled to view it.

 

RockSat-X 2012/2013 Schedule 

09/04/2012

RockSat Payload User’s Guide Released

09/17/2012

Submit Intent to Fly Form (IFF) (Previously Notice of Intent (NOI))

09/24/2012

Initial Down Selections Made

10/15/2012

Conceptual Design Review (CoDR) Due

10/16/2012

Conceptual Design Review (CoDR) Teleconference

10/17/2012

Earnest Deposit of $2,000 due

11/05/2012

Preliminary Design Review (PDR) Due

11/06/2012

Preliminary Design Review (PDR) Teleconference

12/10/2012

Critical Design Review (CDR) Due

12/11/2012

Critical Design Review (CDR) Teleconference

12/15/2012

Post CDR Action Item Generation

1/18/2013

Final Down Select—Flights Awarded

01/28/2013

Post CDR Action Item Review

02/11/2013

Bi-Weekly Teleconferences Begin

02/18/2013

First Installment Due

02/18/2013

Individual Subsystem Testing Reports Due

02/19/2013

Individual Subsystem Testing Reports Teleconference

03/12/201313

Wallops DR (Design Review)and Connectors Sent To

03/18/2013

Full Systems Test Review Report Due

03/19/2012

Full Systems Test Review Report Teleconference

04/08/2013

Final Installment Due

04/15/2013

First DITL Test Report Due

04/16/2012

DITL 1 Teleconferences

05/06/2013

Weekly Teleconferences Begin

05/13/2013

Weekly Teleconference 1

05/13/2013

Second DITL Test Report Due

05/14/2013

Weekly Teleconference 2 (2nd DITL Presentations)

05/20/2013

Weekly Teleconference 3

05/27/2013

Weekly Teleconference 4 (Travel Logistics)

06/03/2013

Integration Readiness Review Packages (IRR) Due

06/04/2013

Integration Readiness Review Telecons with Wallops

06/18/2013

GSE Checkouts At Refuge

06/19>25/2013

Testing and Environmental With Wallops

07/03/2013

Weekly Teleconferences Resume

07/22/2013

Launch Readiness Review Packages (LRR) Due

07/23/2013

Launch Readiness Review Telecons with Wallops

08/06/2013

GSE Checkouts at Refuge Inn

08/07>10/2013

Final Integration at Wallops

08/13/2013

LAUNCH

08/14/2013

Contingency Launch

 

Indicates milestones completed

Indicates milestones with new due dates

Indicates milestones with deliverables

Indicates milestones with Wallops Flight Facility

 

Contingency Launch

Go to top