This schedule provides the dates for all deliverables and important deadlines for the 2016 RockSat-X program. This schedule is subject to change. Launch date is still being determined. Questions can be directed to Jesse Austin at This email address is being protected from spambots. You need JavaScript enabled to view it.

RockSat-X 2015/2016 Schedule

 

September 18th

Intent to Fly Forms Due

September 25th

Initial Down Selections Made/Welcome Letters Sent

October

Conceptual Design Review (CoDR) Teleconferences

October

Earnest Deposit of $2,000 DUE

November

Preliminary Design Review (PDR) Teleconferences

December

Critical Design Review (CDR) Teleconferences

January

Final Down Select—Flights Awarded

Feburary

First Installment Due

Feburary

Subsystem Testing Review (STR) Teleconferences

March

Experiment Decks and Connectors Sent to Customers

March

Integrated Subsystem Testing Review (ISTR) Teleconferences

April

Final Installment Due

April-May

Full Mission Simulation Review (FMSR) Teleconferences

May

Weekly Teleconferences Begin

June

Integration Readiness Review (IRR) Teleconferences

06/21/2015

GSE Checkouts At Refuge

06/22>26/2015

Testing and Environmental With Wallops

July

Weekly Teleconferences Resume

July

Launch Readiness Review Telecons with Wallops

08/09/2015

GSE Checkouts at Refuge Inn

08/10>152015

Final Integration at Wallops

08/16/2015

LAUNCH

08/17/2015

Contingency Launch

 

 <p>
  <center><iframe src="https://www.google.com/calendar/embed?height=600&amp;wkst=1&amp;bgcolor=%23FFFFFF&amp;src=colorado.edu_9hjkgchluavtsv25rmgeu1vg68%40group.calendar.google.com&amp;color=%2323164E&amp;ctz=America%2FDenver" style=" border-width:0 " width="800" height="600" frameborder="0" scrolling="no"></iframe></center>