2012 Schedule

 

Items in Blue are SHOT II 2012 Program Milestones and must be completed. 

Items in Red are suggested milestones and are not required nor is any documentation required.

 

Due Date

Item Status
 02-03-12  SHOT II 2012 User's Guide Released  COMPLETE
 02-22-12  Submit Payload Input Form On-Line  COMPLETE
 03-07-12  Preliminary Payload Design complete  
 03-07-12  SHOT II Registration Begins  COMPLETE
 03-14-12  1st On-Line Progress Report submitted  COMPLETE
 04-04-12  Final Payload Design complete  
 04-11-12  2nd On-line Progress Report submitted  COMPLETE
 04-12-12

 SHOT Telecon: 2 PM MDT (4 PM EDT)

(877)-820-7831, then enter 434477#

 COMPLETE
 05-16-12  Subsystems Build and Testing complete  
 05-23-12  3rd On-line Progress Report submitted  COMPLETE
 05-30-12  SHOT II Registration Deadline  COMPLETE
 06-06-12  Subsystem Integration and Testing complete  
 06-13-12  Full Mission Simulation Test complete  
 06-14-12

 SHOT Telecon: 2 PM MDT (4 PM EDT)

(877)-820-7831, then enter 434477#

 PENDING
 06-20-12  Second Full Mission Simulation Test complete  
 06-27-12  Presentations for Friday (06-29-12) Review submitted
 PENDING
  06-28-12  Travel to Boulder
 
  06-29-12  Presentation to AFRL and COSGC in Boulder
 
  06-30-12  Launch Day
 
 07-01-12  Post Launch Presentations to ARFL and COSGC  
 07-01-12  Workshop concludes mid day