RockSat-C 2019 Schedule

This schedule is subject to change, and this online version supercedes the schedule in the User's Guide. Presentation dates may vary from team to team. Questions can be directed to This email address is being protected from spambots. You need JavaScript enabled to view it.


Fall 2018 Schedule

TBD

Informational Teleconference for RockSat-C and RockSat-X

8/5/2018

RockSat Payload User’s Guide Released

9/17/2018

Deadline to submit Intent to Fly Form (IFF)

9/19/2018

Initial Down Selections Made, Welcome Package Sent Out

10/8-12/2018

Conceptual Design Review (CoDR) Teleconference

10/12/2018

Earnest Payment of $1,000 Due

10/29-11/2/2018

Preliminary Design Review (PDR) Teleconference

12/3-7/2018

Critical Design Review (CDR) Teleconference



Spring 2019 Schedule

1/9/2019

Final Down Select—Flights Awarded

1/21-25/2019

Progress Update Telecon

2/11-15/2019

Subsystem Testing Review Teleconference 

2/11/2019

First payment due

3/4-8/2019

Progress Update Telecon

3/18-22/2019

Integrated Subsystem Testing Review Teleconference

4/11/2019

Final payment due

4/11/2019

RockSat Payload Canisters sent to customers *pending receipt of final payment*

4/15-4/19/2019

Progress Update Telecon

4/29-5/3/2019

Full Mission Simulation Test Report Presentation Telecon

5/20-24/2019

Progress Update Telecon

5/29/2019

Possible Program Telecon

6/3/2019

Preliminary Check-In Procedure Document Due

6/3/2019

Launch Readiness Review Document Due 

6/12/2019

Travel to Wallops Flight Facility

6/13/2019

Visual Inspections at Refuge Inn

06/(14-17)/2019

Vibration/Integration at Wallops

6/19/2019

Presentations to next year’s RockSat

6/20/2019

Launch Day!!

7/12/2019

Preliminary Launch Results Document Due

7/26/2019

Final Report Due

 

 Indicates a deliverable

Indicates a group event/milestone

 Indicates an update teleconference

Indicates payment due