RockSat-C 2020 Schedule

This schedule is subject to change, and this online version supercedes the schedule in the User's Guide. Presentation dates may vary from team to team. Questions can be directed to This email address is being protected from spambots. You need JavaScript enabled to view it.


Fall 2019 Schedule

TBD

Informational Teleconference for RockSat-C and RockSat-X

8/4/2019

RockSat Payload User’s Guide Released

9/16/2019

Deadline to submit Intent to Fly Form (IFF)

9/18/2019

Initial Down Selections Made, Welcome Package Sent Out

10/7-11/2019

Conceptual Design Review (CoDR) Teleconference

10/11/2019

Earnest Payment of $1,000 Due

10/28-11/1/2019

Preliminary Design Review (PDR) Teleconference

12/2-6/2019

Critical Design Review (CDR) Teleconference



Spring 2020 Schedule

1/8/2020

Final Down Select—Flights Awarded

1/20-24/2020

Progress Update Telecon

2/10-14/2020

Subsystem Testing Review Teleconference 

2/10/2020

First payment due

3/2-6/2020

Progress Update Telecon

3/23-27/2020

Integrated Subsystem Testing Review Teleconference

4/10/2020

Final payment due

4/10/2020

RockSat Payload Canisters sent to customers *pending receipt of final payment*

4/13-4/17/2020

Progress Update Telecon

4/27-5/1/2020

Full Mission Simulation Test Report Presentation Telecon

5/18-5/22/2020

Progress Update Telecon

5/27/2020

Possible Program Telecon

6/1/2020

Preliminary Check-In Procedure Document Due

6/1/2020

Launch Readiness Review Document Due 

6/10/2020

Travel to Wallops Flight Facility

6/11/2020

Visual Inspections at Refuge Inn

06/(12-15)/2020

Vibration/Integration at Wallops

6/17/2020

Presentations to next year’s RockSat

6/18/2020

Launch Day!!

7/10/2020

Preliminary Launch Results Document Due

7/24/2020

Final Report Due

 

 Indicates a deliverable

Indicates a group event/milestone

 Indicates an update teleconference

Indicates payment due