Schedule
This schedule provides the dates for all deliverables and important deadlines for the 2022 RockSat-X program. This schedule is subject to change. Launch date is still being determined. Questions can be directed to Abby Schefer at This email address is being protected from spambots. You need JavaScript enabled to view it..
RockSat-X 2021/2022 Schedule
September |
Intent to Fly Forms Due |
September |
Initial Down Selections Made/Welcome Letters Sent |
October |
Conceptual Design Review (CoDR) Teleconferences |
October |
Earnest Deposit of $2,000 DUE |
October -November |
Preliminary Design Review (PDR) Teleconferences |
November -December |
Critical Design Review (CDR) Teleconferences |
January |
Final Down Select—Flights Awarded |
Feburary |
First Installment Due |
Feburary |
Subsystem Testing Review (STR) Teleconferences |
March |
Experiment Decks and Connectors Sent to Customers |
March |
Integrated Subsystem Testing Review (ISTR) Teleconferences |
April |
Final Installment Due |
April-May |
Full Mission Simulation Review (FMSR) Teleconferences |
May |
Weekly Teleconferences Begin |
June |
Visual Verification Check-In (VVC) Teleconferences |
June |
GSE Checkouts At Refuge, Testing and Environmental with Wallops Flight Facility |
July |
Weekly Teleconferences Resume |
July |
Launch Readiness Review Telecons with Wallops |
August |
GSE Checkouts at Refuge Inn, Final integration and testing, Launch! |
Contingency Launch |