Schedule


This schedule provides the dates for all deliverables and important deadlines for the 2022 RockSat-X program. This schedule is subject to change. Launch date is still being determined. Questions can be directed to Abby Schefer at This email address is being protected from spambots. You need JavaScript enabled to view it..

RockSat-X 2021/2022 Schedule

 

September

Intent to Fly Forms Due

September

Initial Down Selections Made/Welcome Letters Sent

October

Conceptual Design Review (CoDR) Teleconferences

October

Earnest Deposit of $2,000 DUE

October -November

Preliminary Design Review (PDR) Teleconferences

November -December

Critical Design Review (CDR) Teleconferences

January

Final Down Select—Flights Awarded

Feburary

First Installment Due

Feburary

Subsystem Testing Review (STR) Teleconferences

March

Experiment Decks and Connectors Sent to Customers

March

Integrated Subsystem Testing Review (ISTR) Teleconferences

April

Final Installment Due

April-May

Full Mission Simulation Review (FMSR) Teleconferences

May

Weekly Teleconferences Begin

June

Visual Verification Check-In (VVC) Teleconferences

June

GSE Checkouts At Refuge, Testing and Environmental with Wallops Flight Facility

July

Weekly Teleconferences Resume

July

Launch Readiness Review Telecons with Wallops

August

GSE Checkouts at Refuge Inn, Final integration and testing, Launch!

 

Contingency Launch